Assessment Year | 2014 |
---|---|
Principal Product | Processed Meat and Poultry |
NAICS | 311615: Poultry Processing |
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
180,000
ft2
|
Annual Production | 70,000,000
lb
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,314,512 | 20,433,600 |
kWh
|
$0.064 |
Electricity Demand | $281,928 | 39,352 |
kW-mo/yr
|
$7.16 |
Natural Gas | $220,288 | 52,442 |
MMBtu
|
$4.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $384,532 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,598 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $688 | $875 |
$688
10,701
kWh
|
- | - | - | |
02 | 2.2437: Recover waste heat from equipment | $1,067 | $847 | - | - | - |
$1,067
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,165 | $5,440 |
$1,165
18,122
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $870 | $4,275 |
$870
13,530
kWh
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,334 | $6,440 |
$1,334
20,746
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,514 | $25,520 |
$14,514
195,786
kWh
|
- | - | - | |
07 | 2.7241: Install outside air damper / economizer on hvac unit | $7,321 | $5,500 |
$7,321
113,724
kWh
|
- | - | - | |
08 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,563 | $280 |
$1,176
18,288
kWh
|
$387
-
kW-mo/yr
|
- | - | |
09 | 2.2511: Insulate bare equipment | $451 | $189 | - | - | - |
$451
-
MMBtu
|
|
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,109 | $30,860 |
$17,109
266,076
kWh
|
- | - | - | |
11 | 2.2414: Use waste heat from hot flue gases to preheat | $9,402 | $32,400 | - | - | - |
$9,402
-
MMBtu
|
|
12 | 2.2136: Install / repair insulation on steam lines | $3,196 | $349 | - | - | - |
$3,196
-
MMBtu
|
|
13 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $28,973 | $22,493 |
$28,973
450,592
kWh
|
- | - | - | |
14 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $296,879 | $1,365,235 | - | - | $296,879 | - | |
TOTAL RECOMMENDED | $384,532 | $1,500,703 |
$73,150
1,107,565
kWh
|
$387
-
kW-mo/yr
|
$296,879 |
$14,116
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,598 | $9,995 |
$3,211
49,940
kWh
|
$387
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs