| Assessment Year | 2014 |
|---|---|
| Principal Product | Electric Motors, Water systems, Fueling systems |
| NAICS | 335312: Motor and Generator Manufacturing |
| SIC | 3621: Motors and Generators |
| Sales Range | $50 M to 100M |
| # of Employees | 335 |
| Plant Area |
332,000
ft2
|
| Annual Production | 75,000
pieces
|
| Production Hrs. Annual | 4,810
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $525,016 | 10,224,900 |
kWh
|
$0.051 |
| Electricity Demand | $161,573 | 19,350 |
kW-mo/yr
|
$8.35 |
| Natural Gas | $133,393 | 22,191 |
MMBtu
|
$6.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $305,581 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,189 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,268 | $1,245 |
$18,268
356,111
kWh
|
- | - | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $6,423 | $7,826 |
$6,423
125,195
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,769 | $168 |
$3,769
73,474
kWh
|
- | - | - | |
| 04 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,649 | $1,014 |
$839
16,351
kWh
|
$810
-
kW-mo/yr
|
- | - | |
| 05 | 2.7231: Use radiant heater for spot heating | $39,930 | $127,500 | - | - | - |
$39,930
-
MMBtu
|
|
| 06 | 2.7243: Improve air circulation with destratification fans / other methods | $8,374 | $29,700 |
$(-1,003.0)
(-19,551)
kWh
|
- | - |
$9,377
-
MMBtu
|
|
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $3,751 | $6,500 | - | - | - |
$3,751
-
MMBtu
|
|
| 08 | 2.6231: Utilize controls to operate equipment only when needed | $402 | $237 |
$402
7,834
kWh
|
- | - | - | |
| 09 | 3.4111: Use closed cycle process to minimize waste water production | $29,530 | $21,500 |
$(-154.0)
(-3,004)
kWh
|
- | - |
$29,684
-
MMBtu
|
|
| 10 | 2.2511: Insulate bare equipment | $304 | $148 |
$304
5,923
kWh
|
- | - | - | |
| 11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $332 | $3,829 |
$332
6,478
kWh
|
- | - | - | |
| 12 | 2.7135: Install occupancy sensors | $587 | $5,092 |
$587
11,445
kWh
|
- | - | - | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $600 | $7,371 |
$600
11,697
kWh
|
- | - | - | |
| 14 | 2.7135: Install occupancy sensors | $36,208 | $5,120 |
$36,208
705,810
kWh
|
- | - | - | |
| 15 | 2.8114: Change rate schedules or other changes in utility service | $155,454 | - | - | - | $155,454 | - | |
| TOTAL RECOMMENDED | $305,581 | $217,250 |
$66,575
1,297,763
kWh
|
$810
-
kW-mo/yr
|
$155,454 |
$82,742
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $39,189 | $40,338 |
$29,002
565,337
kWh
|
$810
-
kW-mo/yr
|
- |
$9,377
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs