ITAC Assessment: OK0879
ITAC logo
ITAC Assessment: OK0879
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Electric Motors, Water systems, Fueling systems
NAICS 335312: Motor and Generator Manufacturing
SIC 3621: Motors and Generators
Sales Range $50
M
to 100
M
# of Employees 335
Plant Area 332,000
ft2
Annual Production 75,000
pieces
Production Hrs. Annual 4,810
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $525,016 10,224,900
kWh
Electricity Demand $161,573 19,350
kW-mo/yr
Natural Gas $133,393 22,191
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $305,581 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,189

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18,268 $1,245 $18,268
356,111
kWh
- - -
02 2.4322: Use or replace with energy efficient substitutes $6,423 $7,826 $6,423
125,195
kWh
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,769 $168 $3,769
73,474
kWh
- - -
04 2.7211: Clean and maintain refrigerant condensers and towers $1,649 $1,014 $839
16,351
kWh
$810
-
kW-mo/yr
- -
05 2.7231: Use radiant heater for spot heating $39,930 $127,500 - - - $39,930
-
MMBtu
06 2.7243: Improve air circulation with destratification fans / other methods $8,374 $29,700 $(-1,003.0)
(-19,551)
kWh
- - $9,377
-
MMBtu
07 2.2414: Use waste heat from hot flue gases to preheat $3,751 $6,500 - - - $3,751
-
MMBtu
08 2.6231: Utilize controls to operate equipment only when needed $402 $237 $402
7,834
kWh
- - -
09 3.4111: Use closed cycle process to minimize waste water production $29,530 $21,500 $(-154.0)
(-3,004)
kWh
- - $29,684
-
MMBtu
10 2.2511: Insulate bare equipment $304 $148 $304
5,923
kWh
- - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $332 $3,829 $332
6,478
kWh
- - -
12 2.7135: Install occupancy sensors $587 $5,092 $587
11,445
kWh
- - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $600 $7,371 $600
11,697
kWh
- - -
14 2.7135: Install occupancy sensors $36,208 $5,120 $36,208
705,810
kWh
- - -
15 2.8114: Change rate schedules or other changes in utility service $155,454 - - - $155,454 -
TOTAL RECOMMENDED $305,581 $217,250 $66,575
1,297,763
kWh
$810
-
kW-mo/yr
$155,454 $82,742
-
MMBtu
TOTAL IMPLEMENTED $39,189 $40,338 $29,002
565,337
kWh
$810
-
kW-mo/yr
- $9,377
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs