Assessment Year | 2013 |
---|---|
Principal Product | Aircraft Parts |
NAICS | 336411: Aircraft Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
60,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 2,630
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $115,834 | 1,781,488 |
kWh
|
$0.065 |
Electricity Demand | $87,273 | 12,675 |
kW-mo/yr
|
$6.89 |
Natural Gas | $23,074 | 2,662 |
MMBtu
|
$8.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,759 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,794 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,232 | - |
$779
11,990
kWh
|
$453
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $623 | $180 |
$623
9,584
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,698 | $29,880 |
$2,530
38,930
kWh
|
$1,168
-
kW-mo/yr
|
- | - | |
04 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $1,473 | $1,128 |
$1,473
22,655
kWh
|
- | - | - | |
05 | 2.7231: Use radiant heater for spot heating | $13,014 | $32,500 | - | - | - |
$13,014
-
MMBtu
|
|
06 | 2.3212: Optimize plant power factor | $12,719 | $11,540 | - | - | $12,719 | - | |
TOTAL RECOMMENDED | $32,759 | $75,228 |
$5,406
83,159
kWh
|
$1,620
-
kW-mo/yr
|
$12,719 |
$13,014
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,794 | $31,188 |
$4,626
71,169
kWh
|
$1,168
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs