ITAC Assessment: OK0847
ITAC logo
ITAC Assessment: OK0847
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Aircraft Parts
NAICS 336411: Aircraft Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 60,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,630
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $115,834 1,781,488
kWh
Electricity Demand $87,273 12,675
kW-mo/yr
Natural Gas $23,074 2,662
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,759 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,794

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,232 - $779
11,990
kWh
$453
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $623 $180 $623
9,584
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,698 $29,880 $2,530
38,930
kWh
$1,168
-
kW-mo/yr
- -
04 2.1121: Use insulation in furnaces to facilitate heating / cooling $1,473 $1,128 $1,473
22,655
kWh
- - -
05 2.7231: Use radiant heater for spot heating $13,014 $32,500 - - - $13,014
-
MMBtu
06 2.3212: Optimize plant power factor $12,719 $11,540 - - $12,719 -
TOTAL RECOMMENDED $32,759 $75,228 $5,406
83,159
kWh
$1,620
-
kW-mo/yr
$12,719 $13,014
-
MMBtu
TOTAL IMPLEMENTED $5,794 $31,188 $4,626
71,169
kWh
$1,168
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs