Assessment Year | 2013 |
---|---|
Principal Product | Clay bricks |
NAICS | 327331: Concrete Block and Brick Manufacturing |
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $5 M to 10M |
# of Employees | 42 |
Plant Area |
110,043
ft2
|
Annual Production | 109,000,000
pieces
|
Production Hrs. Annual | 2,860
hrs
|
Location (State) | Oklahoma |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $309,152 | 6,343,132 |
kWh
|
$0.049 |
Electricity Demand | $108,655 | 18,300 |
kW-mo/yr
|
$5.94 |
Natural Gas | $1,176,121 | 262,246 |
MMBtu
|
$4.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $196,355 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,125 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,514 | $27,500 |
$7,514
153,343
kWh
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,540 | - |
$2,275
46,434
kWh
|
$1,265
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,395 | $1,750 |
$2,395
48,878
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,494 | $33,218 |
$6,423
131,084
kWh
|
$1,071
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $506 | $3,114 |
$506
10,332
kWh
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $667 | $3,677 |
$654
10,335
kWh
|
$13
-
kW-mo/yr
|
- | - | - | |
07 | 2.7232: Replace existing hvac unit with high efficiency model | $2,708 | $5,684 |
$1,617
33,019
kWh
|
$1,091
-
kW-mo/yr
|
- | - | - | |
08 | 2.6232: Install set-back timers | $921 | $1,630 | - | - | - |
$921
-
MMBtu
|
- | |
09 | 2.7211: Clean and maintain refrigerant condensers and towers | $873 | $490 |
$521
10,642
kWh
|
$352
-
kW-mo/yr
|
- | - | - | |
10 | 2.2414: Use waste heat from hot flue gases to preheat | $80,680 | $63,370 | - | - | - |
$80,680
-
MMBtu
|
- | |
11 | 2.4131: Size electric motors for peak operating efficiency | $32,511 | $25,606 |
$32,511
663,493
kWh
|
- | - | - | - | |
12 | 2.4131: Size electric motors for peak operating efficiency | $4,901 | $4,994 |
$4,901
100,001
kWh
|
- | - | - | - | |
13 | 2.3212: Optimize plant power factor | $12,090 | $11,638 | - | - | $12,090 | - | - | |
14 | 2.2511: Insulate bare equipment | $1,275 | $912 | - | - | - |
$1,275
-
MMBtu
|
- | |
15 | 2.2511: Insulate bare equipment | $2,900 | $4,158 | - | - | - |
$2,900
-
MMBtu
|
- | |
16 | 3.1191: Change procedures / equipment / operating conditions | $35,380 | - | - | - | - | - |
$35,380
-
lb
|
|
TOTAL RECOMMENDED | $196,355 | $187,741 |
$59,317
1,207,561
kWh
|
$3,792
-
kW-mo/yr
|
$12,090 |
$85,776
-
MMBtu
|
$35,380
-
lb
|
||
TOTAL IMPLEMENTED | $69,125 | $105,886 |
$53,256
1,086,893
kWh
|
$3,779
-
kW-mo/yr
|
$12,090 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs