Assessment Year | 2011 |
---|---|
Principal Product | Municipal Castings |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
210,000
ft2
|
Annual Production | 60,000
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,006,472 | 66,336,000 |
kWh
|
$0.030 |
Electricity Demand | $987,154 | 242,544 |
kW-mo/yr
|
$4.07 |
Natural Gas | $467,237 | 82,927 |
MMBtu
|
$5.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $363,783 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,919 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $300,355 | $463,765 |
$189,838
4,209,258
kWh
|
$110,518
-
MMBtu
|
|
02 | 2.7135: Install occupancy sensors | $2,088 | $3,375 |
$2,088
46,299
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,179 | $29,929 |
$8,179
181,359
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,927 | $94,677 |
$12,927
286,640
kWh
|
- | |
05 | 2.4224: Upgrade controls on compressors | $18,895 | - |
$18,895
418,954
kWh
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,936 | $4,200 |
$4,936
109,452
kWh
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,980 | $3,757 |
$2,980
96,887
kWh
|
- | |
08 | 2.7241: Install outside air damper / economizer on hvac unit | $6,163 | $12,100 |
$6,163
136,644
kWh
|
- | |
09 | 2.2491: Use cooling air which cools hot work pieces for space heating | $7,260 | $14,928 | - |
$7,260
-
MMBtu
|
|
TOTAL RECOMMENDED | $363,783 | $626,731 |
$246,006
5,485,493
kWh
|
$117,778
-
MMBtu
|
||
TOTAL IMPLEMENTED | $25,919 | $7,575 |
$25,919
574,705
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs