| Assessment Year | 2025 |
|---|---|
| Principal Product | Heavy Duty Breakings/Drivetrain Manufacturing |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $100 M to 500M |
| # of Employees | 330 |
| Plant Area |
275,000
ft2
|
| Annual Production | 7,267,000
pieces
|
| Production Hrs. Annual | 5,355
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $365,205 | 6,191,624 |
kWh
|
$0.059 | |
| Electricity Demand | $238,593 | 15,072 |
kW-mo/yr
|
$15.83 | |
| Electricity Fees | $13,241 | - |
|
- | |
| Natural Gas | $593,454 | 101,705 |
MMBtu
|
$5.84 | |
| Waste Disposal Costs | |||||
| Water Usage | $11,220 | 4,593 |
Tgal
|
$2.44 | |
| Water Disposal | $25,056 | 4,593 |
Tgal
|
$5.46 | |
| Other Liquid (non-haz) | $83,765 | 2,550 |
gal
|
$32.85 | |
| TOTAL YEARLY COSTS | $1,330,534 | ||||
| RECOMMENDED SAVINGS* | $258,134 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $114,962 | - |
$114,962
1,948,504
kWh
|
- | - | - | - | - | |
| 02 | 3.5142: Treat and reuse equipment cleaning solutions | $83,128 | $16,790 | - | - | - |
$4,978
-
Tgal
|
$11,138
-
Tgal
|
$67,012
-
gal
|
|
| 03 | 2.3132: Recharge batteries on during off-peak demand periods | $9,349 | $2,500 |
$3,555
-
kWh
|
$5,794
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.3191: Use demand controller or load shedder | $31,597 | $20,000 | - |
$31,597
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $8,853 | $5,575 | - | - |
$8,853
-
MMBtu
|
- | - | - | |
| 06 | 2.7135: Install occupancy sensors | $6,381 | $4,247 |
$6,381
108,149
kWh
|
- | - | - | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $2,338 | $1,855 |
$2,338
39,627
kWh
|
- | - | - | - | - | |
| 08 | 2.6231: Utilize controls to operate equipment only when needed | $1,526 | $3,257 |
$1,526
25,866
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $258,134 | $54,224 |
$128,762
2,122,146
kWh
|
$37,391
-
kW-mo/yr
|
$8,853
-
MMBtu
|
$4,978
-
Tgal
|
$11,138
-
Tgal
|
$67,012
-
gal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs