Assessment Year | 2010 |
---|---|
Principal Product | Hydraulic Cylinder |
NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
SIC | 3593: Fluid Power Cylinders and Actuators |
Sales Range | $5 M to 10M |
# of Employees | 87 |
Plant Area |
132,500
ft2
|
Annual Production | 92,000
pieces
|
Production Hrs. Annual | 4,355
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $137,339 | 1,917,600 |
kWh
|
$0.072 |
Electricity Demand | $40,301 | 8,699 |
kW-mo/yr
|
$4.63 |
Natural Gas | $61,884 | 9,482 |
MMBtu
|
$6.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,855 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,532 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $12,132 | $75,405 | - |
$12,132
-
MMBtu
|
|
02 | 2.6232: Install set-back timers | $2,786 | $3,239 | - |
$2,786
-
MMBtu
|
|
03 | 2.7492: Use proper thickness of insulation on building envelope | $10,317 | $159,840 | - |
$10,317
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,034 | $12,733 |
$3,034
42,373
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,300 | $68,625 |
$7,300
101,962
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $853 | $4,978 |
$853
11,919
kWh
|
- | |
07 | 2.2437: Recover waste heat from equipment | $653 | $3,006 | - |
$653
-
MMBtu
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,400 | $841 |
$1,400
19,564
kWh
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $380 | $2,280 |
$380
5,318
kWh
|
- | |
TOTAL RECOMMENDED | $38,855 | $330,947 |
$12,967
181,136
kWh
|
$25,888
-
MMBtu
|
||
TOTAL IMPLEMENTED | $13,532 | $76,246 |
$1,400
19,564
kWh
|
$12,132
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs