ITAC Assessment: OK0783
ITAC logo
ITAC Assessment: OK0783
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Peanut Products
NAICS 311911: Roasted Nuts and Peanut Butter Manufacturing
SIC 2068: Salted and Roasted Nuts and Seeds
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 318,000
ft2
Annual Production 145,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,170,350 22,394,101
kWh
Electricity Demand $220,410 43,854
kW-mo/yr
Natural Gas $960,581 101,546
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $176,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $76,541

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7232: Replace existing hvac unit with high efficiency model $29,321 $280,000 $29,321
560,640
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $112 $887 $112
2,132
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,151 $775 $1,151
21,999
kWh
- -
04 2.7241: Install outside air damper / economizer on hvac unit $8,327 $26,066 $8,327
157,500
kWh
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,219 $15,039 $4,219
104,947
kWh
- -
06 2.2414: Use waste heat from hot flue gases to preheat $58,392 $67,320 - - $58,392
-
MMBtu
07 2.1133: Adjust burners for efficient operation $18,978 $3,810 - - $18,978
-
MMBtu
08 2.2424: Use heat in flue gases to preheat products or materials $50,901 $15,708 - - $50,901
-
MMBtu
09 2.4231: Reduce the pressure of compressed air to the minimum required $5,399 - $4,555
113,299
kWh
$844
-
kW-mo/yr
-
TOTAL RECOMMENDED $176,800 $409,605 $47,685
960,517
kWh
$844
-
kW-mo/yr
$128,271
-
MMBtu
TOTAL IMPLEMENTED $76,541 $21,180 $5,818
137,430
kWh
$844
-
kW-mo/yr
$69,879
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs