Assessment Year | 2009 |
---|---|
Principal Product | Rupture Discs |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
20,000
ft2
|
Annual Production | 150,000
lb
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $121,943 | 1,319,240 |
kWh
|
$0.092 |
Natural Gas | $6,405 | 484 |
MMBtu
|
$13.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,941 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $852 | $354 |
$852
9,223
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $1,732 | $3,742 | - |
$1,732
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,733 | - |
$1,733
12,969
kWh
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,005 | $7,542 |
$2,005
21,703
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,300 | $11,120 |
$2,300
24,888
kWh
|
- | |
06 | 2.7425: Clean or color roof to reduce solar load | $804 | $4,800 |
$804
8,702
kWh
|
- | |
07 | 2.2136: Install / repair insulation on steam lines | $4,815 | $820 |
$4,815
52,103
kWh
|
- | |
08 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $700 | $1,825 |
$700
7,567
kWh
|
- | |
TOTAL RECOMMENDED | $14,941 | $30,203 |
$13,209
137,155
kWh
|
$1,732
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,100 | $2,999 |
$8,100
81,862
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs