| Assessment Year | 2008 |
|---|---|
| Principal Product | Plastic pipes and Form-A-Drain |
| NAICS | 326122: Plastics Pipe and Pipe Fitting Manufacturing |
| SIC | 3084: Plastics Pipe |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
340,000
ft2
|
| Annual Production | 8,353,422
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,024,219 | 26,444,450 |
kWh
|
$0.039 |
| Natural Gas | $214,648 | 22,877 |
MMBtu
|
$9.38 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $177,396 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $78,395 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $14,145 | $1,383 |
$14,145
1,247
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,151 | $34,635 |
$14,151
375,804
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $803 | $3,455 |
$803
16,224
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,640 | $7,796 |
$2,640
59,130
kWh
|
- | |
| 05 | 4.611: Begin a practice of predictive / preventative maintenance | $2,068 | $200 |
$2,068
-
kWh
|
- | |
| 06 | 2.7231: Use radiant heater for spot heating | $81,407 | $117,000 | - |
$81,407
-
MMBtu
|
|
| 07 | 2.7261: Install timers and/or thermostats | $46,431 | $6,300 | - |
$46,431
-
MMBtu
|
|
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,751 | - |
$15,751
459,200
kWh
|
- | |
| TOTAL RECOMMENDED | $177,396 | $170,769 |
$49,558
911,605
kWh
|
$127,838
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $78,395 | $7,883 |
$31,964
460,447
kWh
|
$46,431
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs