ITAC Assessment: OK0767
ITAC logo
ITAC Assessment: OK0767
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Plastic pipes and Form-A-Drain
NAICS 326122: Plastics Pipe and Pipe Fitting Manufacturing
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 340,000
ft2
Annual Production 8,353,422
lb
Production Hrs. Annual 8,760
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,024,219 26,444,450
kWh
Natural Gas $214,648 22,877
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $177,396 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $78,395

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2136: Install / repair insulation on steam lines $14,145 $1,383 $14,145
1,247
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,151 $34,635 $14,151
375,804
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $803 $3,455 $803
16,224
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,640 $7,796 $2,640
59,130
kWh
-
05 4.611: Begin a practice of predictive / preventative maintenance $2,068 $200 $2,068
-
kWh
-
06 2.7231: Use radiant heater for spot heating $81,407 $117,000 - $81,407
-
MMBtu
07 2.7261: Install timers and/or thermostats $46,431 $6,300 - $46,431
-
MMBtu
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,751 - $15,751
459,200
kWh
-
TOTAL RECOMMENDED $177,396 $170,769 $49,558
911,605
kWh
$127,838
-
MMBtu
TOTAL IMPLEMENTED $78,395 $7,883 $31,964
460,447
kWh
$46,431
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs