| Assessment Year | 2008 |
|---|---|
| Principal Product | Customized rubber and plastic |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 45 |
| Plant Area |
150,000
ft2
|
| Annual Production | 600,000
lb
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $157,667 | 2,200,800 |
kWh
|
$0.072 |
| Natural Gas | $129,922 | 15,483 |
MMBtu
|
$8.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $72,878 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $3,109 | $5,086 | - |
$3,109
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,596 | $14,878 |
$1,596
29,390
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $477 | $1,165 |
$477
4,836
kWh
|
- | |
| 04 | 2.2136: Install / repair insulation on steam lines | $22,038 | $14,300 | - |
$22,038
-
MMBtu
|
|
| 05 | 4.611: Begin a practice of predictive / preventative maintenance | $7,000 | - |
$7,000
-
kWh
|
- | |
| 06 | 2.2153: Close off unneeded steam lines | $7,161 | - | - |
$7,161
-
MMBtu
|
|
| 07 | 2.2113: Repair or replace steam traps | $28,620 | $23,375 | - |
$28,620
-
MMBtu
|
|
| 08 | 2.1241: Reduce excessive boiler blowdown | $2,877 | - | - |
$2,877
-
MMBtu
|
|
| TOTAL RECOMMENDED | $72,878 | $58,804 |
$9,073
34,226
kWh
|
$63,805
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs