| Assessment Year | 2007 |
|---|---|
| Principal Product | Aircraft transparencies |
| NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
| SIC | 3081: Unsupported Plastics Film and Sheet |
| Sales Range | $10 M to 50M |
| # of Employees | 140 |
| Plant Area |
141,315
ft2
|
| Annual Production | 103,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $352,785 | 6,553,525 |
kWh
|
$0.054 |
| Electricity Demand | $78,131 | 16,505 |
kW-mo/yr
|
$4.73 |
| Electricity Fees | $2,270 | - |
|
- |
| Natural Gas | $1,089,585 | 142,786 |
MMBtu
|
$7.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $161,742 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $59,391 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,891 | $360 |
$7,891
127,143
kWh
|
- | - | - | |
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $57,727 | $3,600 |
$57,727
1,575,510
kWh
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $13,884 | $4,859 | - | - | - |
$13,884
-
MMBtu
|
|
| 04 | 2.2511: Insulate bare equipment | $2,384 | $744 | - | - | - |
$2,384
-
MMBtu
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $2,437 | $1,574 |
$2,437
36,923
kWh
|
- | - | - | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $11,998 | $9,010 |
$6,068
163,571
kWh
|
$5,930
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,171 | $81,808 |
$24,171
366,228
kWh
|
- | - | - | |
| 08 | 2.3212: Optimize plant power factor | $1,509 | $6,760 | - | - | $1,509 | - | |
| 09 | 2.2414: Use waste heat from hot flue gases to preheat | $1,516 | $7,600 | - | - | - |
$1,516
-
MMBtu
|
|
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $609 | $3,125 |
$609
9,230
kWh
|
- | - | - | |
| 11 | 2.7425: Clean or color roof to reduce solar load | $37,616 | $286,361 |
$37,616
569,941
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $161,742 | $405,801 |
$136,519
2,848,546
kWh
|
$5,930
-
kW-mo/yr
|
$1,509 |
$17,784
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $59,391 | $291,580 |
$45,507
697,084
kWh
|
- | - |
$13,884
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs