| Assessment Year | 2004 |
|---|---|
| Principal Product | Wiring Harnesses |
| NAICS | 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $5 M to 10M |
| # of Employees | 123 |
| Plant Area |
55,000
ft2
|
| Annual Production | 14,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $21,759 | 710,054 |
kWh
|
$0.031 |
| Electricity Demand | $26,776 | 2,759 |
kW-mo/yr
|
$9.70 |
| Natural Gas | $18,649 | 2,464 |
MMBtu
|
$7.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $38,512 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $38,512 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.652: Replace existing equipment with more suitable substitutes | $9,780 | $6,150 |
$680
22,233
kWh
|
- | - | $9,100 | - | |
| 02 | 2.7229: Air condition only space necessary | $8,145 | $24,175 |
$4,832
157,918
kWh
|
$3,313
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7241: Install outside air damper / economizer on hvac unit | $5,446 | $23,400 |
$5,446
177,986
kWh
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,440 | $18,681 |
$1,216
39,728
kWh
|
$2,224
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.6232: Install set-back timers | $6,489 | $3,960 | - | - |
$6,489
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $418 | $520 |
$418
13,645
kWh
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $324 | $707 |
$117
3,810
kWh
|
$51
-
kW-mo/yr
|
- | - | $156 | |
| 08 | 2.8118: Check for accuracy of utility / power meters | $4,470 | - | - | - |
$4,470
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $38,512 | $77,593 |
$12,709
415,320
kWh
|
$5,588
-
kW-mo/yr
|
$10,959
-
MMBtu
|
$9,100 | $156 | ||
| TOTAL IMPLEMENTED | $38,512 | $77,593 |
$12,709
415,320
kWh
|
$5,588
-
kW-mo/yr
|
$10,959
-
MMBtu
|
$9,100 | $156 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs