Assessment Year | 2004 |
---|---|
Principal Product | Plastic Products |
NAICS | 326160: Plastics Bottle Manufacturing |
SIC | 3085: Plastics Bottles |
Sales Range | n/a |
# of Employees | 300 |
Plant Area |
400,000
ft2
|
Annual Production | 33,700,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $278,739 | 11,552,800 |
kWh
|
$0.024 |
Electricity Demand | $201,222 | 20,720 |
kW-mo/yr
|
$9.71 |
Natural Gas | $37,333 | 6,540 |
MMBtu
|
$5.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,996 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,375 | $9,750 |
$7,375
306,032
kWh
|
- | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,579 | $887 |
$3,598
149,310
kWh
|
$1,981
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7261: Install timers and/or thermostats | $11,540 | $32,000 |
$11,540
478,804
kWh
|
- | - | - | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,315 | $8,500 | - |
$16,315
-
kW-mo/yr
|
- | - | - | - | |
05 | 4.611: Begin a practice of predictive / preventative maintenance | $4,955 | $150 |
$914
37,913
kWh
|
- |
$4,041
-
MMBtu
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $10,656 | $50,065 |
$10,656
442,175
kWh
|
- | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,200 | - | - | - | - | - | $5,200 | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $391 | $804 |
$391
16,224
kWh
|
- | - | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,550 | $60 | - | - | - |
$2,550
-
Tgal
|
- | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,196 | $360 |
$963
39,946
kWh
|
$531
-
kW-mo/yr
|
- | - | - | $702 | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $567 | $1,377 |
$184
7,621
kWh
|
$101
-
kW-mo/yr
|
- | - | $282 | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,719 | $16,878 |
$1,111
46,085
kWh
|
$613
-
kW-mo/yr
|
- | - | $3,995 | - | |
TOTAL RECOMMENDED | $73,043 | $120,831 |
$36,732
1,524,110
kWh
|
$19,541
-
kW-mo/yr
|
$4,041
-
MMBtu
|
$2,550
-
Tgal
|
$9,477 | $702 | ||
TOTAL IMPLEMENTED | $28,996 | $51,946 |
$16,824
698,044
kWh
|
$2,695
-
kW-mo/yr
|
- | - | $9,477 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs