ITAC Assessment: OK0698
ITAC logo
ITAC Assessment: OK0698
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Plastic Products
NAICS 326160: Plastics Bottle Manufacturing
SIC 3085: Plastics Bottles
Sales Range n/a
# of Employees 300
Plant Area 400,000
ft2
Annual Production 33,700,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $278,739 11,552,800
kWh
Electricity Demand $201,222 20,720
kW-mo/yr
Natural Gas $37,333 6,540
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $73,043 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,996

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,375 $9,750 $7,375
306,032
kWh
- - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,579 $887 $3,598
149,310
kWh
$1,981
-
kW-mo/yr
- - - -
03 2.7261: Install timers and/or thermostats $11,540 $32,000 $11,540
478,804
kWh
- - - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,315 $8,500 - $16,315
-
kW-mo/yr
- - - -
05 4.611: Begin a practice of predictive / preventative maintenance $4,955 $150 $914
37,913
kWh
- $4,041
-
MMBtu
- - -
06 2.7135: Install occupancy sensors $10,656 $50,065 $10,656
442,175
kWh
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $5,200 - - - - - $5,200 -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $391 $804 $391
16,224
kWh
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $2,550 $60 - - - $2,550
-
Tgal
- -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,196 $360 $963
39,946
kWh
$531
-
kW-mo/yr
- - - $702
11 2.7142: Utilize higher efficiency lamps and/or ballasts $567 $1,377 $184
7,621
kWh
$101
-
kW-mo/yr
- - $282 -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $5,719 $16,878 $1,111
46,085
kWh
$613
-
kW-mo/yr
- - $3,995 -
TOTAL RECOMMENDED $73,043 $120,831 $36,732
1,524,110
kWh
$19,541
-
kW-mo/yr
$4,041
-
MMBtu
$2,550
-
Tgal
$9,477 $702
TOTAL IMPLEMENTED $28,996 $51,946 $16,824
698,044
kWh
$2,695
-
kW-mo/yr
- - $9,477 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs