ITAC Assessment: OK0696
ITAC logo
ITAC Assessment: OK0696
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Custom Made Wood Furniture
NAICS 337215: Showcase, Partition, Shelving, and Locker Manufacturing
SIC 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 140,000
ft2
Annual Production 7,800
pieces
Production Hrs. Annual 2,912
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,287 1,523,495
kWh
Electricity Demand $47,317 5,906
kW-mo/yr
Electricity Fees $21,337 -
Natural Gas $51,966 5,552
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,501 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,849

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6232: Install set-back timers $19,051 $4,180 - - $19,051
-
MMBtu
- - -
02 2.7313: Recycle air for heating, ventilation and air conditioning $19,260 $5,950 - - $19,260
-
MMBtu
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,344 $2,100 - $6,344
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,308 $600 $280
10,337
kWh
$81
-
kW-mo/yr
- $600 - $347
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,876 $559 $1,109
40,926
kWh
$959
-
kW-mo/yr
- $(-192.0) - -
06 4.821: Pay bills on time to avoid late fees $1,545 - - - - - $1,545 -
07 4.611: Begin a practice of predictive / preventative maintenance $700 - - - - $700 - -
08 2.7135: Install occupancy sensors $417 $707 $417
15,375
kWh
- - - - -
TOTAL RECOMMENDED $50,501 $14,096 $1,806
66,638
kWh
$7,384
-
kW-mo/yr
$38,311
-
MMBtu
$1,108 $1,545 $347
TOTAL IMPLEMENTED $42,849 $11,396 $1,526
56,301
kWh
$959
-
kW-mo/yr
$38,311
-
MMBtu
$508 $1,545 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs