Assessment Year | 2004 |
---|---|
Principal Product | Custom Made Wood Furniture |
NAICS | 337215: Showcase, Partition, Shelving, and Locker Manufacturing |
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
140,000
ft2
|
Annual Production | 7,800
pieces
|
Production Hrs. Annual | 2,912
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $41,287 | 1,523,495 |
kWh
|
$0.027 |
Electricity Demand | $47,317 | 5,906 |
kW-mo/yr
|
$8.01 |
Electricity Fees | $21,337 | - |
|
- |
Natural Gas | $51,966 | 5,552 |
MMBtu
|
$9.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $50,501 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,849 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $19,051 | $4,180 | - | - |
$19,051
-
MMBtu
|
- | - | - | |
02 | 2.7313: Recycle air for heating, ventilation and air conditioning | $19,260 | $5,950 | - | - |
$19,260
-
MMBtu
|
- | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,344 | $2,100 | - |
$6,344
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,308 | $600 |
$280
10,337
kWh
|
$81
-
kW-mo/yr
|
- | $600 | - | $347 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,876 | $559 |
$1,109
40,926
kWh
|
$959
-
kW-mo/yr
|
- | $(-192.0) | - | - | |
06 | 4.821: Pay bills on time to avoid late fees | $1,545 | - | - | - | - | - | $1,545 | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $700 | - | - | - | - | $700 | - | - | |
08 | 2.7135: Install occupancy sensors | $417 | $707 |
$417
15,375
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $50,501 | $14,096 |
$1,806
66,638
kWh
|
$7,384
-
kW-mo/yr
|
$38,311
-
MMBtu
|
$1,108 | $1,545 | $347 | ||
TOTAL IMPLEMENTED | $42,849 | $11,396 |
$1,526
56,301
kWh
|
$959
-
kW-mo/yr
|
$38,311
-
MMBtu
|
$508 | $1,545 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs