Assessment Year | 2000 |
---|---|
Principal Product | machine tools |
NAICS |
n/a
|
SIC | 3542: Machine Tools, Metal Forming Types |
Sales Range | $1 M to 5M |
# of Employees | 55 |
Plant Area |
n/a
|
Annual Production | 40,000
pieces
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,637 | 448,000 |
kWh
|
$0.082 |
Electricity Demand | $8,411 | 1,943 |
kW-mo/yr
|
$4.33 |
Electricity Fees | $1,890 | - |
|
- |
Natural Gas | $2,512 | 362 |
MMBtu
|
$6.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,460 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,751 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,657 | $360 |
$9,300
113,130
kWh
|
$1,334
-
kW-mo/yr
|
$23 | - | |
02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $1,709 | $95 |
$1,709
20,809
kWh
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $985 | $100 |
$860
10,551
kWh
|
$123
-
kW-mo/yr
|
$2 | - | |
04 | 3.5311: Recover and reuse waste material | $8,109 | $14,542 | - | - | - |
$8,109
-
gal
|
|
TOTAL RECOMMENDED | $21,460 | $15,097 |
$11,869
144,490
kWh
|
$1,457
-
kW-mo/yr
|
$25 |
$8,109
-
gal
|
||
TOTAL IMPLEMENTED | $19,751 | $15,002 |
$10,160
123,681
kWh
|
$1,457
-
kW-mo/yr
|
$25 |
$8,109
-
gal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs