Assessment Year | 2004 |
---|---|
Principal Product | Large Custom HVAC Units |
NAICS | 333415: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipmen |
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
126,000
ft2
|
Annual Production | 187
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,871 | 1,726,020 |
kWh
|
$0.031 |
Electricity Demand | $27,258 | 5,845 |
kW-mo/yr
|
$4.66 |
Electricity Fees | $13,133 | - |
|
- |
Natural Gas | $58,402 | 7,836 |
MMBtu
|
$7.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,157 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,512 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,021 | $1,180 |
$198
5,080
kWh
|
$32
-
kW-mo/yr
|
- | $791 | - | |
02 | 3.4116: Meter recycled water (to reduce sewer charges) | $857 | - | - | - | - | - |
$857
-
Tgal
|
|
03 | 2.7135: Install occupancy sensors | $1,079 | $2,156 |
$719
18,447
kWh
|
$360
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,433 | $252 |
$1,433
36,739
kWh
|
- | - | - | - | |
05 | 2.6232: Install set-back timers | $853 | $822 | - | - |
$853
-
MMBtu
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $1,521 | $472 | - | - |
$1,521
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,393 | $758 |
$590
15,124
kWh
|
$296
-
kW-mo/yr
|
- | $507 | - | |
TOTAL RECOMMENDED | $8,157 | $5,640 |
$2,940
75,390
kWh
|
$688
-
kW-mo/yr
|
$2,374
-
MMBtu
|
$1,298 |
$857
-
Tgal
|
||
TOTAL IMPLEMENTED | $2,512 | $2,408 |
$2,152
55,186
kWh
|
$360
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs