ITAC Assessment: OK0678
ITAC logo
ITAC Assessment: OK0678
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Pressure Control Valves for Oil & Gas Field
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range less than $500
k
# of Employees 160
Plant Area 120,000
ft2
Annual Production 18,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $129,381 4,774,200
kWh
Electricity Demand $87,172 11,515
kW-mo/yr
Electricity Fees $61,948 -
Natural Gas $79,818 11,170
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,405 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,783

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,075 $823 $3,531
130,280
kWh
- - - - $(-456.0) -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,817 $3,690 $1,817
67,033
kWh
- - - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $5,836 $10,835 $6,292
232,170
kWh
- - - - $(-456.0) -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $13,162 $800 - - $13,162 - - - -
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $22,602 $28,350 $14,765
544,836
kWh
$24,478
-
kW-mo/yr
- $(-16,641.0)
-
MMBtu
- - -
06 2.2414: Use waste heat from hot flue gases to preheat $5,188 $12,597 - - - $5,188
-
MMBtu
- - -
07 2.6232: Install set-back timers $3,347 $2,200 - - - $3,347
-
MMBtu
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $2,847 $14,078 $325
11,980
kWh
$157
-
kW-mo/yr
- - - $1,934 $431
09 2.7142: Utilize higher efficiency lamps and/or ballasts $546 $1,154 $135
4,993
kWh
- - - - $346 $65
10 3.5316: Contract a wood pallet recycling company $2,985 - - - - - $2,985
-
lb
- -
TOTAL RECOMMENDED $61,405 $74,527 $26,865
991,292
kWh
$24,635
-
kW-mo/yr
$13,162 $(-8,106.0)
-
MMBtu
$2,985
-
lb
$1,368 $496
TOTAL IMPLEMENTED $27,783 $19,502 $11,775
434,476
kWh
- $13,162 $3,347
-
MMBtu
- $(-566.0) $65
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs