ITAC Assessment: MI0430
ITAC logo
ITAC Assessment: MI0430
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Industrial Metals and Manufacturing Products
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3444: Sheet Metal Work
Sales Range $100
M
to 500
M
# of Employees 62
Plant Area 100,000
ft2
Annual Production 72,000,000
lb
Production Hrs. Annual 5,772
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,869 829,600
kWh
Electricity Demand $34,594 2,814
kW-mo/yr
Electricity Fees $23,399 -
LPG $36,400 1,070
MMBtu
TOTAL YEARLY COSTS $150,262
RECOMMENDED SAVINGS* $40,697 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,569

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7221: Lower temperature during the winter season and vice-versa $25,630 $580 $18,549
276,851
kWh
$7,081
-
kW-mo/yr
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,475 $1,920 - $4,475
-
kW-mo/yr
03 2.6218: Turn off equipment when not in use $3,086 $3,360 $3,086
46,064
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,567 $3,751 $1,670
24,919
kWh
$897
-
kW-mo/yr
05 2.7243: Improve air circulation with destratification fans / other methods $1,834 $7,288 $1,330
19,850
kWh
$504
-
kW-mo/yr
06 2.4239: Eliminate or reduce compressed air usage $1,813 $470 $1,312
19,589
kWh
$501
-
kW-mo/yr
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,292 $1,980 $879
13,114
kWh
$413
-
kW-mo/yr
TOTAL RECOMMENDED $40,697 $19,349 $26,826
400,387
kWh
$13,871
-
kW-mo/yr
TOTAL IMPLEMENTED $30,569 $10,318 $22,070
329,404
kWh
$8,499
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs