Assessment Year | 2003 |
---|---|
Principal Product | Coiled Steel Products |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 92 |
Plant Area |
323,000
ft2
|
Annual Production | 7,000
ton
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,611 | 1,710,033 |
kWh
|
$0.041 |
Electricity Fees | $25,385 | - |
|
- |
Natural Gas | $17,972 | 2,257 |
MMBtu
|
$7.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,354 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,774 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $1,275 | $263 | - | - |
$1,275
-
MMBtu
|
- | - | |
02 | 4.611: Begin a practice of predictive / preventative maintenance | $4,300 | - | - | - | - | $4,300 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,249 | $631 |
$7,284
129,838
kWh
|
$3,229
-
kW-mo/yr
|
- | $(-264.0) | - | |
04 | 2.7135: Install occupancy sensors | $112 | $131 |
$112
1,997
kWh
|
- | - | - | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $4,838 | $2,000 | - | - | - | - | $4,838 | |
06 | 2.4133: Use most efficient type of electric motors | $2,275 | $15,280 |
$2,274
40,535
kWh
|
- | - | - | $1 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $996 | $5,100 |
$821
14,627
kWh
|
$175
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $309 | $505 |
$279
4,980
kWh
|
$30
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $24,354 | $23,910 |
$10,770
191,977
kWh
|
$3,434
-
kW-mo/yr
|
$1,275
-
MMBtu
|
$4,036 | $4,839 | ||
TOTAL IMPLEMENTED | $20,774 | $3,025 |
$7,396
131,835
kWh
|
$3,229
-
kW-mo/yr
|
$1,275
-
MMBtu
|
$4,036 | $4,838 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs