ITAC Assessment: OK0658
ITAC logo
ITAC Assessment: OK0658
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Automotive Door Seals
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 430
Plant Area 250,000
ft2
Annual Production 25
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma
View Case Study

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $691,547 19,108,800
kWh
Electricity Demand $337,113 41,511
kW-mo/yr
Electricity Fees $3,245 -
Natural Gas $150,003 30,832
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $154,935 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $82,742

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4224: Upgrade controls on compressors $51,704 $45,000 $37,204
1,200,118
kWh
$14,500
-
kW-mo/yr
- - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $25,266 - - $25,266
-
kW-mo/yr
- - -
03 2.7221: Lower temperature during the winter season and vice-versa $11,031 - - - $11,031
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,978 $367 $2,963
95,580
kWh
$1,155
-
kW-mo/yr
- $(-1,140.0) -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,150 $5,273 $5,150
166,120
kWh
- - - -
06 2.2614: Use cooling tower or economizer to replace chiller cooling $30,454 $60,000 $30,454
982,415
kWh
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $9,028 $117 $6,832
220,402
kWh
$2,664
-
kW-mo/yr
- - $(-468.0)
08 2.7142: Utilize higher efficiency lamps and/or ballasts $5,609 $30,876 $2,541
81,967
kWh
$1,843
-
kW-mo/yr
- - $1,225
09 2.7135: Install occupancy sensors $6,270 $2,004 $6,270
202,272
kWh
- - - -
10 2.6241: Reduce temperature of process equipment when on standby $7,445 - $4,453
143,640
kWh
- $2,992
-
MMBtu
- -
TOTAL RECOMMENDED $154,935 $143,637 $95,867
3,092,514
kWh
$45,428
-
kW-mo/yr
$14,023
-
MMBtu
$(-1,140.0) $757
TOTAL IMPLEMENTED $82,742 $83,520 $54,128
1,746,057
kWh
$17,498
-
kW-mo/yr
$11,031
-
MMBtu
$(-1,140.0) $1,225
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs