Assessment Year | 2002 |
---|---|
Principal Product | Medium Density Fiberboard |
NAICS |
n/a
|
SIC | 2493: Reconstituted Wood Products |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
166,840
ft2
|
Annual Production | 400,000
thousand feet
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,454,752 | 33,636,325 |
kWh
|
$0.043 |
Natural Gas | $1,197,843 | 241,525 |
MMBtu
|
$4.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $379,428 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $251,676 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $42,712 | $2,250 |
$42,712
1,123,974
kWh
|
- | - | |
02 | 2.2511: Insulate bare equipment | $29,330 | $9,344 | - |
$29,330
-
MMBtu
|
- | |
03 | 2.2441: Preheat boiler makeup water with waste process heat | $21,369 | $15,150 | - |
$21,369
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,658 | $3,635 |
$16,658
438,380
kWh
|
- | - | |
05 | 2.2511: Insulate bare equipment | $11,788 | $9,041 | - |
$11,788
-
MMBtu
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,412 | $3,349 |
$2,412
63,484
kWh
|
- | - | |
07 | 4.445: Install equipment to move product | $166,400 | $208,754 | - | - | $166,400 | |
08 | 2.7141: Lower light fixtures in high ceiling areas | $87,000 | $5,400 | - | - | $87,000 | |
09 | 2.6232: Install set-back timers | $1,446 | $372 | - |
$1,446
-
MMBtu
|
- | |
10 | 2.7135: Install occupancy sensors | $313 | $395 |
$313
8,237
kWh
|
- | - | |
TOTAL RECOMMENDED | $379,428 | $257,690 |
$62,095
1,634,075
kWh
|
$63,933
-
MMBtu
|
$253,400 | ||
TOTAL IMPLEMENTED | $251,676 | $229,761 |
$42,712
1,123,974
kWh
|
$42,564
-
MMBtu
|
$166,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs