ITAC Assessment: OK0614
ITAC logo
ITAC Assessment: OK0614
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product HVAC equipment
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $50
M
to 100
M
# of Employees 330
Plant Area 150,000
ft2
Annual Production 2,000,000
thousand feet
Production Hrs. Annual 2,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $159,536 5,206,400
kWh
Electricity Demand $95,764 17,345
kW-mo/yr
Electricity Fees $8,670 -
Natural Gas $59,792 15,887
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,958 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,756

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.3132: Recharge batteries on during off-peak demand periods $1,325 $335 - $1,325
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,500 $6,100 $8,500
279,300
kWh
- - -
03 2.2511: Insulate bare equipment $5,656 $9,700 $2,332
76,200
kWh
- $3,324
-
MMBtu
-
04 2.7135: Install occupancy sensors $377 $3,700 $377
12,305
kWh
- - -
05 4.132: Purchase new equipment to reduce material use / cost $9,100 $4,000 - - $3,800
-
MMBtu
$5,300
TOTAL RECOMMENDED $24,958 $23,835 $11,209
367,805
kWh
$1,325
-
kW-mo/yr
$7,124
-
MMBtu
$5,300
TOTAL IMPLEMENTED $14,756 $13,700 $2,332
76,200
kWh
- $7,124
-
MMBtu
$5,300
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs