| Assessment Year | 2002 |
|---|---|
| Principal Product | Calcium Oxide |
| NAICS |
n/a
|
| SIC | 3274: Lime |
| Sales Range | $5 M to 10M |
| # of Employees | 51 |
| Plant Area |
n/a
|
| Annual Production | 361,200
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $514,307 | 13,998,600 |
kWh
|
$0.037 |
| Electricity Demand | $106,029 | 3,500 |
kW-mo/yr
|
$30.29 |
| Electricity Fees | $252 | - |
|
- |
| Natural Gas | $200,927 | 49,230 |
MMBtu
|
$4.08 |
| Coal | $2,000,000 | 1,196,000 |
MMBtu
|
$1.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $331,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $194,258 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $49,032 | $32,834 | n/a |
$44,979
820,822
kWh
|
$4,053
-
kW-mo/yr
|
- | - | - | - |
| 02 | 2.6232: Install set-back timers | $1,658 | $238 | - | - |
$1,658
-
MMBtu
|
- | - | - | |
| 03 | 2.8114: Change rate schedules or other changes in utility service | $36,000 | $64,800 | n/a | - | - | - | - | $36,000 | - |
| 04 | 2.3212: Optimize plant power factor | $2,661 | $8,000 | n/a |
$2,661
72,511
kWh
|
- | - | - | - | - |
| 05 | 2.7135: Install occupancy sensors | $265 | $350 |
$265
7,207
kWh
|
- | - | - | - | - | |
| 06 | 2.3311: Replace dc equipment with ac equipment | $47,600 | $71,935 | n/a | - | - | - | $30,000 | - | $17,600 |
| 07 | 2.2515: Use optimum thickness insulation | $194,258 | $42,750 | - | - |
$194,258
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $331,474 | $220,907 |
$47,905
900,540
kWh
|
$4,053
-
kW-mo/yr
|
$195,916
-
MMBtu
|
$30,000 | $36,000 | $17,600 | ||
| TOTAL IMPLEMENTED | $194,258 | $42,750 | - | - |
$194,258
-
MMBtu
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs