Assessment Year | 2002 |
---|---|
Principal Product | Activated Carbon for liquid purification |
NAICS |
n/a
|
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 88 |
Plant Area |
152,245
ft2
|
Annual Production | 40,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $288,906 | 15,909,838 |
kWh
|
$0.018 |
Electricity Demand | $248,895 | 26,200 |
kW-mo/yr
|
$9.50 |
Electricity Fees | $1,217 | - |
|
- |
Natural Gas | $1,147,250 | 270,183 |
MMBtu
|
$4.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,139,769 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $857,118 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,287 | $552 |
$54
2,965
kWh
|
$39
-
kW-mo/yr
|
- | - | $269 | $925 | - | |
02 | 2.7135: Install occupancy sensors | $351 | $720 |
$351
19,282
kWh
|
- | - | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,451 | $2,995 |
$375
20,592
kWh
|
$1,010
-
kW-mo/yr
|
- | - | - | $66 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $766 | $35,173 |
$1,076
72,770
kWh
|
$774
-
kW-mo/yr
|
- | - | - | $(-1,084.0) | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $94,595 | $103,140 |
$55,019
3,023,042
kWh
|
$39,576
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2161: Optimize operation of multi-stage vacuum steam jets | $276,478 | $200,000 | - | - |
$(-214,695.0)
-
MMBtu
|
$491,173
-
MMBtu
|
- | - | - | |
07 | 2.2423: Install waste heat boiler to produce steam | $752,359 | $502,500 | - | - | - |
$762,104
-
MMBtu
|
- | - |
$(-9,745.0)
-
Tgal
|
|
08 | 2.7231: Use radiant heater for spot heating | $5,822 | $11,440 | - | - |
$5,822
-
MMBtu
|
- | - | - | - | |
09 | 2.6232: Install set-back timers | $6,660 | $3,570 | - | - |
$6,660
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,139,769 | $860,090 |
$56,875
3,138,651
kWh
|
$41,399
-
kW-mo/yr
|
$(-202,213.0)
-
MMBtu
|
$1,253,277
-
MMBtu
|
$269 | $(-93.0) |
$(-9,745.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $857,118 | $647,930 |
$56,524
3,119,369
kWh
|
$41,399
-
kW-mo/yr
|
$6,660
-
MMBtu
|
$762,104
-
MMBtu
|
$269 | $(-93.0) |
$(-9,745.0)
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Energy Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs