Assessment Year | 2001 |
---|---|
Principal Product | Gray & ductile iron castings |
NAICS |
n/a
|
SIC | 3322: Malleable Iron Foundries |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
110,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $248,467 | 5,801,600 |
kWh
|
$0.043 |
Electricity Demand | $31,693 | - |
|
- |
Electricity Fees | $9,648 | - |
|
- |
Natural Gas | $182,205 | 25,097 |
MMBtu
|
$7.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $180,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,747 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,953 | $300 |
$20,253
470,992
kWh
|
- | $(-300.0) | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,400 | - |
$1,400
32,585
kWh
|
- | - | |
03 | 2.7444: Close holes and openings in building such as broken windows | $1,994 | $3,700 | - |
$1,994
-
MMBtu
|
- | |
04 | 2.6232: Install set-back timers | $11,800 | $3,370 | - |
$11,800
-
MMBtu
|
- | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $28,600 | $5,000 | - | - | $28,600 | |
06 | 4.112: Replace old machine with new automatic multi-station tool | $115,000 | $180,000 | - | - | $115,000 | |
07 | 2.2437: Recover waste heat from equipment | $1,542 | $1,800 | - |
$1,542
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $180,289 | $194,170 |
$21,653
503,577
kWh
|
$15,336
-
MMBtu
|
$143,300 | ||
TOTAL IMPLEMENTED | $33,747 | $7,370 |
$20,253
470,992
kWh
|
$13,794
-
MMBtu
|
$(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs