Assessment Year | 2001 |
---|---|
Principal Product | Carbide Drills and Inserts |
NAICS |
n/a
|
SIC | 3445: |
Sales Range | $10 M to 50M |
# of Employees | 126 |
Plant Area |
52,000
ft2
|
Annual Production | 2,700,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $138,659 | 6,563,712 |
kWh
|
$0.021 |
Electricity Demand | $54,164 | 12,750 |
kW-mo/yr
|
$4.25 |
Electricity Fees | $76,896 | - |
|
- |
Natural Gas | $6,050 | 2,172 |
MMBtu
|
$2.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $105,619 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $102,977 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,900 | $360 |
$2,210
104,675
kWh
|
$890
-
kW-mo/yr
|
- | $(-200.0) | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $5,851 | $84 |
$3,730
126,000
kWh
|
$1,071
-
kW-mo/yr
|
- | - | - | $1,050 | |
03 | 2.7135: Install occupancy sensors | $376 | $476 |
$376
17,280
kWh
|
- | - | - | - | - | |
04 | 2.6232: Install set-back timers | $2,642 | $1,408 | - | - |
$2,642
-
MMBtu
|
- | - | - | |
05 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $868 | $230 |
$472
22,350
kWh
|
$396
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2622: Replace existing chiller with high efficiency model | $39,782 | $95,000 |
$28,358
1,344,000
kWh
|
$11,424
-
kW-mo/yr
|
- | - | - | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $53,200 | $30,400 | - | - | - | $42,000 | $11,200 | - | |
TOTAL RECOMMENDED | $105,619 | $127,958 |
$35,146
1,614,305
kWh
|
$13,781
-
kW-mo/yr
|
$2,642
-
MMBtu
|
$41,800 | $11,200 | $1,050 | ||
TOTAL IMPLEMENTED | $102,977 | $126,550 |
$35,146
1,614,305
kWh
|
$13,781
-
kW-mo/yr
|
- | $41,800 | $11,200 | $1,050 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs