ITAC Assessment: OK0620
ITAC logo
ITAC Assessment: OK0620
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Heat Exchanger
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $1
M
to 5
M
# of Employees 34
Plant Area 33,350
ft2
Annual Production 420
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $17,804 320,280
kWh
Electricity Fees $313 -
Natural Gas $12,233 1,965
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,391 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,102

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,592 $615 $223
6,588
kWh
$39
-
kW-mo/yr
- $300 $1,030
02 2.7142: Utilize higher efficiency lamps and/or ballasts $238 $1,470 $100
2,962
kWh
$74
-
kW-mo/yr
- - $64
03 2.7135: Install occupancy sensors $129 $240 $129
3,828
kWh
- - - -
04 2.2135: Repair and eliminate steam leaks $1,442 $200 $828
24,500
kWh
$614
-
kW-mo/yr
- - -
05 2.6232: Install set-back timers $8,700 $1,170 - - $8,700
-
MMBtu
- -
06 2.2437: Recover waste heat from equipment $1,130 $40 - - $1,130
-
MMBtu
- -
07 3.2176: Increase use of automation $4,160 $38,900 - - - $4,160 -
TOTAL RECOMMENDED $17,391 $42,635 $1,280
37,878
kWh
$727
-
kW-mo/yr
$9,830
-
MMBtu
$4,460 $1,094
TOTAL IMPLEMENTED $13,102 $3,495 $1,151
34,050
kWh
$727
-
kW-mo/yr
$9,830
-
MMBtu
$300 $1,094
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs