Assessment Year | 2001 |
---|---|
Principal Product | Plastic Packaging |
NAICS |
n/a
|
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
175,000
ft2
|
Annual Production | 68,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $855,741 | 34,464,000 |
kWh
|
$0.025 |
Electricity Demand | $343,244 | 55,970 |
kW-mo/yr
|
$6.13 |
Electricity Fees | $282,984 | - |
|
- |
Natural Gas | $17,779 | 3,012 |
MMBtu
|
$5.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $178,232 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,653 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $792 | $310 |
$82
3,294
kWh
|
$28
-
kW-mo/yr
|
- | - | $168 | - | $514 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,585 | $18,400 |
$1,974
79,609
kWh
|
$828
-
kW-mo/yr
|
- | - | - | - | $2,783 | |
03 | 2.7135: Install occupancy sensors | $816 | $878 |
$816
32,890
kWh
|
- | - | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,184 | $200 |
$2,453
98,910
kWh
|
$831
-
kW-mo/yr
|
- | - | $(-100.0) | - | - | |
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,191 | $1,423 |
$891
35,916
kWh
|
$300
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 3.3125: Use distillation, evaporation to remove contaminants | $38,340 | $12,500 | - | - | - |
$38,340
-
gal
|
- | - | - | |
07 | 2.7242: Change zone reheat coils to variable air volume boxes | $68,500 | $15,000 |
$68,500
2,761,986
kWh
|
- | - | - | - | - | - | |
08 | 2.7226: Use computer programs to optimize hvac performance | $2,200 | $1,326 | - |
$2,200
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,082 | $3,936 |
$2,303
92,856
kWh
|
$779
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $12,577 | $3,000 |
$1,013
40,827
kWh
|
- |
$11,564
-
MMBtu
|
- | - | - | - | |
11 | 2.6231: Utilize controls to operate equipment only when needed | $11,523 | $10,275 |
$8,610
347,170
kWh
|
$2,913
-
kW-mo/yr
|
- | - | - | - | - | |
12 | 4.114: Add/modify equipment to improve drying process | $29,565 | $10,000 | - | - | - | - | $29,565 | - | - | |
13 | 4.821: Pay bills on time to avoid late fees | $877 | - | - | - | - | - | - | $877 | - | |
TOTAL RECOMMENDED | $178,232 | $77,248 |
$86,642
3,493,458
kWh
|
$7,879
-
kW-mo/yr
|
$11,564
-
MMBtu
|
$38,340
-
gal
|
$29,633 | $877 | $3,297 | ||
TOTAL IMPLEMENTED | $99,653 | $30,111 |
$80,658
3,252,187
kWh
|
$5,972
-
kW-mo/yr
|
$11,564
-
MMBtu
|
- | $68 | $877 | $514 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs