ITAC Assessment: OK0617
ITAC logo
ITAC Assessment: OK0617
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Asphalt
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $5
M
to 10
M
# of Employees 15
Plant Area 400,000
ft2
Annual Production 200,000
ton
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,499 946,261
kWh
Electricity Fees $2,063 -
Natural Gas $358,603 101,671
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,505 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $658

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Increase in Production Savings
01 2.7135: Install occupancy sensors $335 $304 $335
4,563
kWh
- - -
02 2.6232: Install set-back timers $323 $439 - $323
-
MMBtu
- -
03 2.1221: Replace obsolete burners with more efficient ones $17,946 $30,145 - $17,946
-
MMBtu
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $409 $354 $409
5,576
kWh
- - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,337 $9,259 $8,337
113,579
kWh
- - -
06 4.445: Install equipment to move product $1,170 $1,000 - - $1,170 -
07 2.2437: Recover waste heat from equipment $23,985 $27,632 - $2,385
-
MMBtu
- $21,600
TOTAL RECOMMENDED $52,505 $69,133 $9,081
123,718
kWh
$20,654
-
MMBtu
$1,170 $21,600
TOTAL IMPLEMENTED $658 $743 $335
4,563
kWh
$323
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs