ITAC Assessment: OK0612
ITAC logo
ITAC Assessment: OK0612
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Water & Oil Well Drilling Equipment
NAICS
n/a
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 314,279
ft2
Annual Production 1,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,020 3,608,400
kWh
Electricity Fees $142,315 -
Natural Gas $108,331 22,510
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $108,333 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $90,113

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.6232: Install set-back timers $88,000 $17,542 - - $88,000
-
MMBtu
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,333 $577 $189
7,190
kWh
$307
-
kW-mo/yr
- - $210 - $627
03 3.3125: Use distillation, evaporation to remove contaminants $2,772 $5,200 - - - $2,772
-
gal
- - -
04 4.821: Pay bills on time to avoid late fees $463 - - - - - - $463 -
05 2.2135: Repair and eliminate steam leaks $1,650 $720 $637
14,545
kWh
$1,013
-
kW-mo/yr
- - - - -
06 2.3212: Optimize plant power factor $14,115 $5,150 - $14,115
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $108,333 $29,189 $826
21,735
kWh
$15,435
-
kW-mo/yr
$88,000
-
MMBtu
$2,772
-
gal
$210 $463 $627
TOTAL IMPLEMENTED $90,113 $18,262 $637
14,545
kWh
$1,013
-
kW-mo/yr
$88,000
-
MMBtu
- - $463 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs