| Assessment Year | 1987 |
|---|---|
| Principal Product | METAL ELECTRICAL ENCLOSURES |
| NAICS |
n/a
|
| SIC | 3469: Metal Stampings, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 115 |
| Plant Area |
n/a
|
| Annual Production | 1,000,000
lb
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $81,489 | 1,317,409 |
kWh
|
$0.062 |
| Natural Gas | $55,134 | 13,688 |
MMBtu
|
$4.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,418 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,551 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $867 | $1,200 | - |
$867
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $573 | $540 |
$573
9,379
kWh
|
- | |
| 03 | 2.2511: Insulate bare equipment | $683 | $900 | - |
$683
-
MMBtu
|
|
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,672 | $45 |
$605
9,672
kWh
|
$2,067
-
MMBtu
|
|
| 05 | 2.8121: Apply for tax-free status for energy purchases | $3,517 | $250 |
$1,767
-
kWh
|
$1,750
-
MMBtu
|
|
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,069 | $500 |
$1,069
-
kWh
|
- | |
| 07 | 2.7226: Use computer programs to optimize hvac performance | $12,647 | $2,000 | - |
$12,647
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $390 | $796 |
$390
6,448
kWh
|
- | |
| TOTAL RECOMMENDED | $22,418 | $6,231 |
$4,404
25,499
kWh
|
$18,014
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $21,551 | $5,031 |
$4,404
25,499
kWh
|
$17,147
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs