ITAC Assessment: OK0601
ITAC logo
ITAC Assessment: OK0601
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Oil well completion tools
NAICS
n/a
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 147,550
ft2
Annual Production 0
units
Production Hrs. Annual 5,430
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,340 1,710,727
kWh
Electricity Fees $34,408 -
Natural Gas $14,749 1,319
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $219,758 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,605

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $684 $3,500 $684
12,603
kWh
- -
02 2.4225: Install common header on compressors $11,372 $3,000 $11,372
207,210
kWh
- -
03 2.7134: Use photocell controls $17,881 $5,000 $17,881
325,615
kWh
- -
04 4.513: Re-arrange equipment layout to reduce labor costs $140,000 $100,000 - - $140,000
05 4.513: Re-arrange equipment layout to reduce labor costs $29,952 - - - $29,952
06 4.111: Add equipment/ operators to reduce production bottleneck $14,040 $35,000 - - $14,040
07 3.5248: Separate and recycle scrap metal to foundry or for sale $5,829 - - $5,829
-
lb
-
TOTAL RECOMMENDED $219,758 $146,500 $29,937
545,428
kWh
$5,829
-
lb
$183,992
TOTAL IMPLEMENTED $32,605 $43,500 $18,565
338,218
kWh
- $14,040
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs