Assessment Year | 2000 |
---|---|
Principal Product | Oil well completion tools |
NAICS |
n/a
|
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
147,550
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,430
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,340 | 1,710,727 |
kWh
|
$0.035 |
Electricity Fees | $34,408 | - |
|
- |
Natural Gas | $14,749 | 1,319 |
MMBtu
|
$11.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $219,758 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,605 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $684 | $3,500 |
$684
12,603
kWh
|
- | - | |
02 | 2.4225: Install common header on compressors | $11,372 | $3,000 |
$11,372
207,210
kWh
|
- | - | |
03 | 2.7134: Use photocell controls | $17,881 | $5,000 |
$17,881
325,615
kWh
|
- | - | |
04 | 4.513: Re-arrange equipment layout to reduce labor costs | $140,000 | $100,000 | - | - | $140,000 | |
05 | 4.513: Re-arrange equipment layout to reduce labor costs | $29,952 | - | - | - | $29,952 | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $14,040 | $35,000 | - | - | $14,040 | |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $5,829 | - | - |
$5,829
-
lb
|
- | |
TOTAL RECOMMENDED | $219,758 | $146,500 |
$29,937
545,428
kWh
|
$5,829
-
lb
|
$183,992 | ||
TOTAL IMPLEMENTED | $32,605 | $43,500 |
$18,565
338,218
kWh
|
- | $14,040 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs