ITAC Assessment: OK0593
ITAC logo
ITAC Assessment: OK0593
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Blast cleaning equipment
NAICS
n/a
SIC 3569: General Industrial Machinery and Equipment, Not Elsewhere
Sales Range $10
M
to 50
M
# of Employees 81
Plant Area 58,000
ft2
Annual Production 200
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,644 648,007
kWh
Natural Gas $9,574 2,329
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,692 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,390

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.7135: Install occupancy sensors $302 $749 $302
4,103
kWh
- - - -
02 2.6232: Install set-back timers $5,562 $1,110 - $5,562
-
MMBtu
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $537 $1,160 $537
5,862
kWh
- - - -
04 2.8114: Change rate schedules or other changes in utility service $3,126 - - - - - $3,126
05 4.511: Expand operations into unused space $5,850 $7,000 - - - $5,850 -
06 3.8135: Use low voc or water based paint $1,315 $1,350 - - $1,315
-
gal
- -
TOTAL RECOMMENDED $16,692 $11,369 $839
9,965
kWh
$5,562
-
MMBtu
$1,315
-
gal
$5,850 $3,126
TOTAL IMPLEMENTED $16,390 $10,620 $537
5,862
kWh
$5,562
-
MMBtu
$1,315
-
gal
$5,850 $3,126
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs