| Assessment Year | 2000 |
|---|---|
| Principal Product | Rebuilt Transmissions |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 600 |
| Plant Area |
220,000
ft2
|
| Annual Production | 146,332
pieces
|
| Production Hrs. Annual | 4,940
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $152,348 | 6,566,530 |
kWh
|
$0.023 |
| Electricity Demand | $119,234 | - |
|
- |
| Natural Gas | $76,726 | 26,593 |
MMBtu
|
$2.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $214,164 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,792 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $315 | $1,900 |
$315
13,834
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,477 | $4,942 |
$1,477
64,185
kWh
|
- | - | - | - | |
| 03 | 2.7135: Install occupancy sensors | $875 | $136 | - |
$875
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.1331: Burn a less expensive grade of fuel | $9,042 | $230,000 | - | - |
$9,042
-
MMBtu
|
- | - | |
| 05 | 3.3125: Use distillation, evaporation to remove contaminants | $181,048 | $59,400 | - | - | - |
$181,048
-
gal
|
- | |
| 06 | 4.323: Optimize lot sizes to reduce inventory carrying costs | $21,407 | $30,000 | - | - | - | - | $21,407 | |
| TOTAL RECOMMENDED | $214,164 | $326,378 |
$1,792
78,019
kWh
|
$875
-
kW-mo/yr
|
$9,042
-
MMBtu
|
$181,048
-
gal
|
$21,407 | ||
| TOTAL IMPLEMENTED | $1,792 | $6,842 |
$1,792
78,019
kWh
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs