| Assessment Year | 1998 |
|---|---|
| Principal Product | Industrial Valves |
| NAICS |
n/a
|
| SIC | 3491: Industrial Valves |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
266,000
ft2
|
| Annual Production | 18,000,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Arkansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,003,759 | 31,286,929 |
kWh
|
$0.032 |
| Electricity Demand | $1,174,894 | 94,879 |
kW-mo/yr
|
$12.38 |
| Natural Gas | $323,217 | 72,812 |
MMBtu
|
$4.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $109,879 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $93,232 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,477 | $500 |
$4,396
137,456
kWh
|
$4,081
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $637 | $1,060 |
$269
8,499
kWh
|
$368
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,475 | - |
$1,330
41,618
kWh
|
$3,145
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $3,792 | $850 |
$1,819
56,858
kWh
|
$1,973
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $40,673 | $1,200 |
$17,278
540,152
kWh
|
$23,395
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $39,295 | $91,825 |
$35,917
1,122,802
kWh
|
$3,378
-
kW-mo/yr
|
- | - | - | |
| 07 | 3.8142: Distill contaminated solvents for reuse | $3,600 | $6,000 |
$(-148.0)
(-879)
kWh
|
- |
$2,592
-
gal
|
$(-1,244.0) | $2,400 | |
| 08 | 4.513: Re-arrange equipment layout to reduce labor costs | $4,787 | $1,000 | - | - | - | $4,787 | - | |
| 09 | 4.513: Re-arrange equipment layout to reduce labor costs | $4,143 | - | - | - | - | $4,143 | - | |
| TOTAL RECOMMENDED | $109,879 | $102,435 |
$60,861
1,906,506
kWh
|
$36,340
-
kW-mo/yr
|
$2,592
-
gal
|
$7,686 | $2,400 | ||
| TOTAL IMPLEMENTED | $93,232 | $94,525 |
$57,591
1,800,410
kWh
|
$30,854
-
kW-mo/yr
|
- | $4,787 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs