Assessment Year | 1999 |
---|---|
Principal Product | Shopping carts |
NAICS |
n/a
|
SIC | 3496: Miscellaneous Fabricated Wire Products |
Sales Range | $10 M to 50M |
# of Employees | 386 |
Plant Area |
510,000
ft2
|
Annual Production | 450,000
pieces
|
Production Hrs. Annual | 5,640
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $375,486 | 18,164,127 |
kWh
|
$0.021 |
Electricity Demand | $384,703 | - |
|
- |
Natural Gas | $231,533 | 78,980 |
MMBtu
|
$2.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $142,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $52,988 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,100 | $7,000 | - | - |
$8,100
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $13,117 | $6,500 |
$6,208
295,428
kWh
|
$6,909
-
kW-mo/yr
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $2,681 | $1,000 |
$1,850
39,566
kWh
|
$831
-
kW-mo/yr
|
- | - | - | |
04 | 3.6114: Use precipitating agents in waste water treatment that produce the least quantity of waste | $14,440 | $30,000 | - | - | - |
$14,440
-
lb
|
- | |
05 | 4.423: Move product using mechanical means | $81,900 | $50,000 | - | - | - | - | $81,900 | |
06 | 4.424: Improve space comfort conditioning | $22,750 | $50,000 | - | - | - | - | $22,750 | |
TOTAL RECOMMENDED | $142,988 | $144,500 |
$8,058
334,994
kWh
|
$7,740
-
kW-mo/yr
|
$8,100
-
MMBtu
|
$14,440
-
lb
|
$104,650 | ||
TOTAL IMPLEMENTED | $52,988 | $87,500 |
$8,058
334,994
kWh
|
$7,740
-
kW-mo/yr
|
- |
$14,440
-
lb
|
$22,750 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs