Assessment Year | 1999 |
---|---|
Principal Product | Oil Country Tubulars |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
125,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $253,777 | 5,393,318 |
kWh
|
$0.047 |
Electricity Demand | $31,289 | - |
|
- |
Electricity Fees | $1,696 | - |
|
- |
Natural Gas | $325,589 | 117,519 |
MMBtu
|
$2.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,914 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,121 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|
01 | 2.2442: Preheat combustion air with waste heat | $18,365 | $50,500 | - |
$18,365
-
MMBtu
|
- | |
02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,750 | $9,700 | - | - |
$9,750
-
lb
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,239 | $25,525 |
$5,239
64,478
kWh
|
- | - | |
04 | 2.7135: Install occupancy sensors | $2,935 | $2,490 |
$2,935
61,841
kWh
|
- | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,743 | $8,000 | - | - |
$2,743
-
lb
|
|
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,107 | $1,500 |
$2,107
44,549
kWh
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $775 | $500 |
$775
16,413
kWh
|
- | - | |
TOTAL RECOMMENDED | $41,914 | $98,215 |
$11,056
187,281
kWh
|
$18,365
-
MMBtu
|
$12,493
-
lb
|
||
TOTAL IMPLEMENTED | $8,121 | $27,525 |
$8,121
125,440
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs