ITAC Assessment: OK0583
ITAC logo
ITAC Assessment: OK0583
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Oil Country Tubulars
NAICS
n/a
SIC 3498: Fabricated Pipe and Pipe Fittings
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 125,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 4,940
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $253,777 5,393,318
kWh
Electricity Demand $31,289 -
Electricity Fees $1,696 -
Natural Gas $325,589 117,519
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,914 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,121

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.2442: Preheat combustion air with waste heat $18,365 $50,500 - $18,365
-
MMBtu
-
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $9,750 $9,700 - - $9,750
-
lb
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,239 $25,525 $5,239
64,478
kWh
- -
04 2.7135: Install occupancy sensors $2,935 $2,490 $2,935
61,841
kWh
- -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $2,743 $8,000 - - $2,743
-
lb
06 2.4231: Reduce the pressure of compressed air to the minimum required $2,107 $1,500 $2,107
44,549
kWh
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $775 $500 $775
16,413
kWh
- -
TOTAL RECOMMENDED $41,914 $98,215 $11,056
187,281
kWh
$18,365
-
MMBtu
$12,493
-
lb
TOTAL IMPLEMENTED $8,121 $27,525 $8,121
125,440
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs