| Assessment Year | 1987 |
|---|---|
| Principal Product | SHELL & TUBE HEAT EXCHANGERS |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $5 M to 10M |
| # of Employees | 107 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,300
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $113,303 | 2,247,069 |
kWh
|
$0.050 |
| Natural Gas | $30,501 | 8,166 |
MMBtu
|
$3.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,672 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,002 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $57 | $43 |
$57
1,172
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,929 | $24,647 |
$10,966
273,154
kWh
|
- | $(-37.0) | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $638 | - |
$578
18,757
kWh
|
- | $60 | |
| 04 | 2.2437: Recover waste heat from equipment | $7,800 | $1,155 | - |
$7,800
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,319 | - |
$2,629
84,701
kWh
|
- | $(-310.0) | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $870 | $230 |
$90
2,931
kWh
|
- | $780 | |
| 07 | 2.7261: Install timers and/or thermostats | $1,059 | $450 |
$1,059
34,291
kWh
|
- | - | |
| TOTAL RECOMMENDED | $23,672 | $26,525 |
$15,379
415,006
kWh
|
$7,800
-
MMBtu
|
$493 | ||
| TOTAL IMPLEMENTED | $15,002 | $25,140 |
$15,289
412,075
kWh
|
- | $(-287.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs