ITAC Assessment: OK0579
ITAC logo
ITAC Assessment: OK0579
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Candy
NAICS
n/a
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 255
Plant Area 140,000
ft2
Annual Production 50,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,110 7,670,868
kWh
Electricity Demand $31,289 -
Electricity Fees $18,142 -
Natural Gas $195,166 70,515
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $594,920 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.441: Install automatic packing equipment $274,676 $82,000 - - - - $274,676 -
02 4.441: Install automatic packing equipment $137,338 $18,000 - - - - $137,338 -
03 4.111: Add equipment/ operators to reduce production bottleneck $68,469 $800 - - - - $68,469 -
04 2.4231: Reduce the pressure of compressed air to the minimum required $41,137 $70,000 $41,137
1,517,878
kWh
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $21,509 $38,395 $6,029
571,219
kWh
$15,480
-
kW-mo/yr
- - - -
06 4.111: Add equipment/ operators to reduce production bottleneck $22,857 $6,912 - - - - $22,857 -
07 2.4231: Reduce the pressure of compressed air to the minimum required $8,932 - $3,176
212,485
kWh
$5,756
-
kW-mo/yr
- - - -
08 2.2136: Install / repair insulation on steam lines $7,002 $14,553 $7,002
741,501
kWh
- - - - -
09 2.4221: Install compressor air intakes in coolest locations $5,238 $3,250 $1,862
124,560
kWh
$3,376
-
kW-mo/yr
- - - -
10 2.3212: Optimize plant power factor $2,368 $1,500 - - $2,368 - - -
11 3.1162: Use less wasteful packaging $1,850 $2,956 - - - $1,850
-
lb
- -
12 4.821: Pay bills on time to avoid late fees $1,409 - - - - - - $1,409
13 2.7142: Utilize higher efficiency lamps and/or ballasts $1,239 $850 $924
11,723
kWh
$315
-
kW-mo/yr
- - - -
14 3.6193: Install equipment (eg compactor) to reduce disposal costs $896 - - - - $896
-
lb
- -
TOTAL RECOMMENDED $594,920 $239,216 $60,130
3,179,366
kWh
$24,927
-
kW-mo/yr
$2,368 $2,746
-
lb
$503,340 $1,409
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs