| Assessment Year | 1999 |
|---|---|
| Principal Product | Candy |
| NAICS |
n/a
|
| SIC | 2064: Candy and Other Confectionery Products |
| Sales Range | $10 M to 50M |
| # of Employees | 255 |
| Plant Area |
140,000
ft2
|
| Annual Production | 50,000,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $220,110 | 7,670,868 |
kWh
|
$0.029 |
| Electricity Demand | $31,289 | - |
|
- |
| Electricity Fees | $18,142 | - |
|
- |
| Natural Gas | $195,166 | 70,515 |
MMBtu
|
$2.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $594,920 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.441: Install automatic packing equipment | $274,676 | $82,000 | - | - | - | - | $274,676 | - | |
| 02 | 4.441: Install automatic packing equipment | $137,338 | $18,000 | - | - | - | - | $137,338 | - | |
| 03 | 4.111: Add equipment/ operators to reduce production bottleneck | $68,469 | $800 | - | - | - | - | $68,469 | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $41,137 | $70,000 |
$41,137
1,517,878
kWh
|
- | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,509 | $38,395 |
$6,029
571,219
kWh
|
$15,480
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $22,857 | $6,912 | - | - | - | - | $22,857 | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,932 | - |
$3,176
212,485
kWh
|
$5,756
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.2136: Install / repair insulation on steam lines | $7,002 | $14,553 |
$7,002
741,501
kWh
|
- | - | - | - | - | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $5,238 | $3,250 |
$1,862
124,560
kWh
|
$3,376
-
kW-mo/yr
|
- | - | - | - | |
| 10 | 2.3212: Optimize plant power factor | $2,368 | $1,500 | - | - | $2,368 | - | - | - | |
| 11 | 3.1162: Use less wasteful packaging | $1,850 | $2,956 | - | - | - |
$1,850
-
lb
|
- | - | |
| 12 | 4.821: Pay bills on time to avoid late fees | $1,409 | - | - | - | - | - | - | $1,409 | |
| 13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,239 | $850 |
$924
11,723
kWh
|
$315
-
kW-mo/yr
|
- | - | - | - | |
| 14 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $896 | - | - | - | - |
$896
-
lb
|
- | - | |
| TOTAL RECOMMENDED | $594,920 | $239,216 |
$60,130
3,179,366
kWh
|
$24,927
-
kW-mo/yr
|
$2,368 |
$2,746
-
lb
|
$503,340 | $1,409 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs