| Assessment Year | 1999 |
|---|---|
| Principal Product | Electric motor repair |
| NAICS |
n/a
|
| SIC | 3621: Motors and Generators |
| Sales Range | $5 M to 10M |
| # of Employees | 32 |
| Plant Area |
125,000
ft2
|
| Annual Production | 520
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $21,772 | 771,688 |
kWh
|
$0.028 |
| Electricity Demand | $25,430 | - |
|
- |
| Electricity Fees | $3,944 | - |
|
- |
| Natural Gas | $30,033 | 6,960 |
MMBtu
|
$4.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,106 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Water Disposal Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.4154: Eliminate leaks in water lines and valves | $1,087 | $500 | n/a | - | - |
$1,087
-
Tgal
|
- |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $294 | $110 | n/a |
$294
4,689
kWh
|
- | - | - |
| 03 | 2.7135: Install occupancy sensors | $325 | $2,165 | n/a |
$325
10,551
kWh
|
- | - | - |
| 04 | 4.211: Consider use / purchase of bulk materials where possible | $7,200 | $1,680 | n/a | - | - | - | $7,200 |
| 05 | 2.3512: De-energize excess transformer capacity | $9,766 | $12,000 | n/a | - | $9,766 | - | - |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $434 | $6,549 | n/a |
$434
7,034
kWh
|
- | - | - |
| TOTAL RECOMMENDED | $19,106 | $23,004 |
$1,053
22,274
kWh
|
$9,766 |
$1,087
-
Tgal
|
$7,200 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Water Disposal Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs