ITAC Assessment: OK0573
ITAC logo
ITAC Assessment: OK0573
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Winches, Wheel Drives, and Hoists
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $50
M
to 100
M
# of Employees 60
Plant Area 160,000
ft2
Annual Production 7,000
pieces
Production Hrs. Annual 6,800
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,105 7,092,614
kWh
Electricity Demand $14,747 -
Natural Gas $71,347 20,311
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,334 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,161

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,582 $16,945 $5,582
135,991
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,215 $45,737 $15,215
279,601
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,266 $1,900 $3,266
109,320
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $545 $246 $545
14,068
kWh
- -
05 3.5311: Recover and reuse waste material $13,831 $8,000 - $13,831
-
lb
-
06 2.4322: Use or replace with energy efficient substitutes $6,895 $34,750 - - $6,895
TOTAL RECOMMENDED $45,334 $107,578 $24,608
538,980
kWh
$13,831
-
lb
$6,895
TOTAL IMPLEMENTED $10,161 $36,650 $3,266
109,320
kWh
- $6,895
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs