ITAC Assessment: OK0567
ITAC logo
ITAC Assessment: OK0567
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Folding aluminum camping furniture
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 125
Plant Area 135,000
ft2
Annual Production 2,500,000
lb
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,160 486,518
kWh
Electricity Fees $324 -
Natural Gas $18,068 2,749
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,737 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $84,941

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.7122: Disconnect ballasts $49 $429 $49
2,052
kWh
- - -
02 2.2437: Recover waste heat from equipment $657 $2,127 - $657
-
MMBtu
- -
03 2.4221: Install compressor air intakes in coolest locations $139 $171 $139
5,862
kWh
- - -
04 4.311: Schedule deliveries according to demand $4,000 - - - - $4,000
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $382 $529 $382
24,326
kWh
- - -
06 4.131: Modify process to reduce material use/cost $4,010 $15,000 - - - $4,010
07 3.1192: Reduce scrap production $76,500 $40,000 - - $76,500
-
lb
-
TOTAL RECOMMENDED $85,737 $58,256 $570
32,240
kWh
$657
-
MMBtu
$76,500
-
lb
$8,010
TOTAL IMPLEMENTED $84,941 $55,958 $431
26,378
kWh
- $76,500
-
lb
$8,010
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs