Assessment Year | 1999 |
---|---|
Principal Product | Folding aluminum camping furniture |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 125 |
Plant Area |
135,000
ft2
|
Annual Production | 2,500,000
lb
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,160 | 486,518 |
kWh
|
$0.052 |
Electricity Fees | $324 | - |
|
- |
Natural Gas | $18,068 | 2,749 |
MMBtu
|
$6.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $85,737 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $84,941 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7122: Disconnect ballasts | $49 | $429 |
$49
2,052
kWh
|
- | - | - | |
02 | 2.2437: Recover waste heat from equipment | $657 | $2,127 | - |
$657
-
MMBtu
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $139 | $171 |
$139
5,862
kWh
|
- | - | - | |
04 | 4.311: Schedule deliveries according to demand | $4,000 | - | - | - | - | $4,000 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $382 | $529 |
$382
24,326
kWh
|
- | - | - | |
06 | 4.131: Modify process to reduce material use/cost | $4,010 | $15,000 | - | - | - | $4,010 | |
07 | 3.1192: Reduce scrap production | $76,500 | $40,000 | - | - |
$76,500
-
lb
|
- | |
TOTAL RECOMMENDED | $85,737 | $58,256 |
$570
32,240
kWh
|
$657
-
MMBtu
|
$76,500
-
lb
|
$8,010 | ||
TOTAL IMPLEMENTED | $84,941 | $55,958 |
$431
26,378
kWh
|
- |
$76,500
-
lb
|
$8,010 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs