ITAC Assessment: OK0559
ITAC logo
ITAC Assessment: OK0559
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Fabricated glass products
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 98
Plant Area 60,000
ft2
Annual Production 3,500
thousand feet
Production Hrs. Annual 4,160
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,262 3,676,436
kWh
Electricity Demand $32,333 -
Electricity Fees $3,300 -
Natural Gas $4,979 671
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,597 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $318

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 4.112: Replace old machine with new automatic multi-station tool $32,230 $140,000 - - $20,800 $11,430
02 3.5315: Lease / purchase baler; sell cardboard to recycler $7,376 $7,900 - $7,376
-
lb
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $673 - $673
16,413
kWh
- - -
04 2.4221: Install compressor air intakes in coolest locations $318 $660 $318
7,913
kWh
- - -
TOTAL RECOMMENDED $40,597 $148,560 $991
24,326
kWh
$7,376
-
lb
$20,800 $11,430
TOTAL IMPLEMENTED $318 $660 $318
7,913
kWh
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs