ITAC Assessment: OK0532
ITAC logo
ITAC Assessment: OK0532
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Tickets
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 352
Plant Area 175,000
ft2
Annual Production 150,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,668 4,814,478
kWh
Electricity Demand $50,684 11,806
kW-mo/yr
Electricity Fees $3,564 -
Natural Gas $20,622 3,902
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,096 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,964

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $732 $1,738 $732
31,067
kWh
- - -
02 2.2511: Insulate bare equipment $723 $10,000 $500
21,102
kWh
$223
-
kW-mo/yr
- -
03 4.441: Install automatic packing equipment $62,400 $160,000 - - - $62,400
04 4.652: Replace existing equipment with more suitable substitutes $171 $480 $69
2,931
kWh
$17
-
kW-mo/yr
- $85
05 3.1161: Eliminate/reduce an operation $8,070 $3,000 - - $8,070
-
lb
-
TOTAL RECOMMENDED $72,096 $175,218 $1,301
55,100
kWh
$240
-
kW-mo/yr
$8,070
-
lb
$62,485
TOTAL IMPLEMENTED $8,964 $13,480 $569
24,033
kWh
$240
-
kW-mo/yr
$8,070
-
lb
$85
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs