Assessment Year | 1991 |
---|---|
Principal Product | WELDED STEEL TUBING |
NAICS |
n/a
|
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $10 M to 50M |
# of Employees | 163 |
Plant Area |
n/a
|
Annual Production | 800
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $277,485 | 5,502,052 |
kWh
|
$0.050 |
Natural Gas | $106,452 | 26,875 |
MMBtu
|
$3.96 |
Fuel Oil #2 | $15,029 | 2,744 |
MMBtu
|
$5.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $185,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $185,866 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1332: Convert combustion equipment to burn natural gas | $2,221 | $6,000 | - |
$(-4,187.0)
-
MMBtu
|
$6,408
-
MMBtu
|
- | |
02 | 2.4322: Use or replace with energy efficient substitutes | $145,812 | - |
$15,812
418,523
kWh
|
- | - | $130,000 | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,976 | - |
$2,976
-
kWh
|
- | - | - | |
04 | 2.6241: Reduce temperature of process equipment when on standby | $34,857 | - | - |
$34,857
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $185,866 | $6,000 |
$18,788
418,523
kWh
|
$30,670
-
MMBtu
|
$6,408
-
MMBtu
|
$130,000 | ||
TOTAL IMPLEMENTED | $185,866 | $6,000 |
$18,788
418,523
kWh
|
$30,670
-
MMBtu
|
$6,408
-
MMBtu
|
$130,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs