| Assessment Year | 1996 |
|---|---|
| Principal Product | Weld fittings |
| NAICS |
n/a
|
| SIC | 3449: Miscellaneous Structural Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
74,000
ft2
|
| Annual Production | 6,000
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,333 | 2,093,201 |
kWh
|
$0.029 |
| Electricity Demand | $43,928 | 5,393 |
kW-mo/yr
|
$8.15 |
| Electricity Fees | $4,062 | - |
|
- |
| Natural Gas | $185,244 | 78,552 |
MMBtu
|
$2.36 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,357 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,853 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7231: Use radiant heater for spot heating | $3,504 | $18,090 | - | - |
$3,504
-
MMBtu
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $113 | $124 | - | - |
$113
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,844 | $260 |
$2,844
97,011
kWh
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,173 | $797 |
$716
24,326
kWh
|
$457
-
kW-mo/yr
|
- | - | |
| 05 | 3.1191: Change procedures / equipment / operating conditions | $20,723 | $15,008 | - | - | - |
$20,723
-
Tgal
|
|
| TOTAL RECOMMENDED | $28,357 | $34,279 |
$3,560
121,337
kWh
|
$457
-
kW-mo/yr
|
$3,617
-
MMBtu
|
$20,723
-
Tgal
|
||
| TOTAL IMPLEMENTED | $24,853 | $16,189 |
$3,560
121,337
kWh
|
$457
-
kW-mo/yr
|
$113
-
MMBtu
|
$20,723
-
Tgal
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs