Assessment Year | 1996 |
---|---|
Principal Product | Livestock Feeds |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $5 M to 10M |
# of Employees | 26 |
Plant Area |
25,000
ft2
|
Annual Production | 51,000
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $90,004 | 1,771,102 |
kWh
|
$0.051 |
Electricity Demand | $1,301 | 7,290 |
kW-mo/yr
|
$0.18 |
Electricity Fees | $1,866 | - |
|
- |
Natural Gas | $93,170 | 10,888 |
MMBtu
|
$8.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,237 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,063 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,063 | $1,976 |
$3,188
58,617
kWh
|
$875
-
kW-mo/yr
|
- | - | |
02 | 2.2511: Insulate bare equipment | $1,262 | $2,915 | - | - |
$1,262
-
MMBtu
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,084 | $5,000 | - | - |
$3,084
-
MMBtu
|
- | |
05 | 2.7135: Install occupancy sensors | $100 | $160 |
$100
1,172
kWh
|
- | - | - | |
06 | 2.6232: Install set-back timers | $308 | $156 | - | - |
$308
-
MMBtu
|
- | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $420 | - | - | - | - |
$420
-
lb
|
|
TOTAL RECOMMENDED | $9,237 | $10,207 |
$3,288
59,789
kWh
|
$875
-
kW-mo/yr
|
$4,654
-
MMBtu
|
$420
-
lb
|
||
TOTAL IMPLEMENTED | $4,063 | $1,976 |
$3,188
58,617
kWh
|
$875
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs