ITAC Assessment: OK0499
ITAC logo
ITAC Assessment: OK0499
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Livestock Feeds
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $5
M
to 10
M
# of Employees 26
Plant Area 25,000
ft2
Annual Production 51,000
ton
Production Hrs. Annual 4,160
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $90,004 1,771,102
kWh
Electricity Demand $1,301 7,290
kW-mo/yr
Electricity Fees $1,866 -
Natural Gas $93,170 10,888
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,237 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,063

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,063 $1,976 $3,188
58,617
kWh
$875
-
kW-mo/yr
- -
02 2.2511: Insulate bare equipment $1,262 $2,915 - - $1,262
-
MMBtu
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $3,084 $5,000 - - $3,084
-
MMBtu
-
05 2.7135: Install occupancy sensors $100 $160 $100
1,172
kWh
- - -
06 2.6232: Install set-back timers $308 $156 - - $308
-
MMBtu
-
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $420 - - - - $420
-
lb
TOTAL RECOMMENDED $9,237 $10,207 $3,288
59,789
kWh
$875
-
kW-mo/yr
$4,654
-
MMBtu
$420
-
lb
TOTAL IMPLEMENTED $4,063 $1,976 $3,188
58,617
kWh
$875
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs