ITAC Assessment: OK0497
ITAC logo
ITAC Assessment: OK0497
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Newspapers
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $50
M
to 100
M
# of Employees 1,000
Plant Area 500,000
ft2
Annual Production 146,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $439,396 18,916,765
kWh
Electricity Demand $279,687 38,916
kW-mo/yr
Electricity Fees $719,083 -
Natural Gas $100,710 33,292
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,775 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,187

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings
01 3.5316: Contract a wood pallet recycling company $9,000 - - $9,000
-
lb
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,269 $4,587 $7,269
289,566
kWh
-
03 2.7135: Install occupancy sensors $1,213 $396 $1,213
48,359
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $1,106 $1,965 $1,106
43,962
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $187 $50 $187
7,327
kWh
-
TOTAL RECOMMENDED $18,775 $6,998 $9,775
389,214
kWh
$9,000
-
lb
TOTAL IMPLEMENTED $9,187 $50 $187
7,327
kWh
$9,000
-
lb
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs