ITAC Assessment: UU0241
ITAC logo
ITAC Assessment: UU0241
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Health and Beauty
NAICS 325620: Toilet Preparation Manufacturing
SIC 2844: Perfumes, Cosmetics, and Other Toilet Preparations
Sales Range $100
M
to 500
M
# of Employees 10
Plant Area 15,500
ft2
Annual Production 198
ton
Production Hrs. Annual 2,069
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $74,679 605,120
kWh
Electricity Demand $39,584 3,326
kW-mo/yr
Electricity Fees $9,819 -
Natural Gas $26,677 2,544
MMBtu
Waste Disposal Costs
Water Usage $18,298 2,115
Tgal
Water Disposal $126,000 4
Tgal
TOTAL YEARLY COSTS $295,057
RECOMMENDED SAVINGS* $33,639 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,809

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.8113: Purchase gas directly from a contract gas supplier $8,700 $12,200 - - - - $8,700
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,030 $17,040 $6,280
51,030
kWh
$1,750
-
kW-mo/yr
- - -
03 2.6218: Turn off equipment when not in use $7,740 $10,080 $7,740
62,920
kWh
- - - -
04 2.8121: Apply for tax-free status for energy purchases $4,480 $6,000 - - $4,480 - -
05 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $2,300 $7,800 - - - $2,300
-
MMBtu
-
06 2.2511: Insulate bare equipment $1,150 $3,710 - - - $1,150
-
MMBtu
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $650 $2,200 $180
1,470
kWh
$470
-
kW-mo/yr
- - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $589 $750 $563
4,570
kWh
$26
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $33,639 $59,780 $14,763
119,990
kWh
$2,246
-
kW-mo/yr
$4,480 $3,450
-
MMBtu
$8,700
TOTAL IMPLEMENTED $12,809 $16,830 $8,303
67,490
kWh
$26
-
kW-mo/yr
$4,480 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs